We’re Hiring!

Why You Want to Work for Western Allied Mechanical

Genesis Station

Daly City, CA
Project Summary

Nine Story, 380,000 Square Foot Office to Lab Conversion in a partially occupied building. The existing condenser water and heating hot water plant were up-sized during a two-week shutdown of the building. New lab exhaust fans on the roof and water-cooled AC units on each floor were installed to support the new labs. New ductwork and piping risers were installed in the building and on the building exterior. Five and a half floors (approximately 220,000 sq ft) were converted from Office to Spec 50% Office/ 50% Lab use while the other floors remained occupied.

Market Sectors
  • Retrofit
  • Life Sciences
  • Commercial
Services
  • BIM/VDC
  • Engineering
  • Mechanical
  • Special Projects
Connect With Us

Let us know about your next project or partnering needs.